1. Home
  2. Further Reading
  3. Modified Rational Method, Step-by-Step

Modified Rational Method, Step-by-Step

If you’ve read the previous article, “Rational Method vs. SCS Method“,  then you’ll have some background information on this one. Here we are going to dig a little deeper into that comparison and walk you through the steps we used to arrive at the Modified Rational method results.

This article will also teach you how to perform a pre- and post-development study using the Modified Rational method.

We could have chosen any of the other two methods (Standard Rational or NRCS) but the Modified Rational can be confusing to some who have never used it before. So hopefully this will enlighten. The process for the pond sizing and outlet structure design is basically the same, regardless of the method(s) used.

A 10-acre Site in Atlanta, Georgia

To recap, our scenario is based on modeling a pre- and post development project on a ten-acre site in Atlanta, GA that transforms a “Meadow in good condition” to an “Industrial site”. We modeled using NOAA intensity and precipitation rainfall for the 2, 10 and 100-year return periods. Pre- and post-developed runoff hydrographs were created using the appropriate runoff coefficients (C) and Times of Concentration (Tc).

The pre-developed hydrograph was created using the Standard Rational method. The post-developed hydrograph was developed using the Modified Rational method and using the peak Qs of the pre-developed. More about this below.

After that, a new detention pond was designed using the pre-developed peak Qs for the target release rates. The post-developed Modified Rational hydrograph was the pond’s inflow hydrograph.

Here are the inputs and the resulting basin model:

Modified Rational Data Inputs

Area (ac)10.00
Pre-developedRunoff Coefficient (C) 0.30
Tc (min)30
Post-developedRunoff Coefficient (C)0.85
Tc (min)12

Modified Rational Method example

Step 1. Create Pre-developed Hydrograph

The Standard Rational is always used for the pre-developed because all we want are peak Qs for use in the post-developed hydrograph. We added a Rational method icon by clicking on the Rational Method button on the top toolbar. Next, we added the following data and clicked [Compute].

Noticed we used the Standard Rational method here

The peak Qs are 7, 10 and 15 cfs for the 2, 10 and 100-year events respectively. These are the Target Qs we’ll use to create the post-developed hydrograph in the next step.

Here is the resulting 100-yr hydrograph shown on the Charts tab but all we really need are the peak Qs.

Modified Rational Method example

Step 2. Create Post-developed Hydrograph

Repeating Step 1, we added a second Rational method icon by clicking on the Rational Method button on the top Ribbon toolbar and added the following data.

The Modified Rational was selected for the Calculation Method and we entered the Peak Qs from Step 1 for the Qtargets. Note that we left the Storm Duration Factors blank (TBD). The software computes these for us after clicking [Compute].

Tip

If you did not make a note of the peak Qs from Step 1, click on the Table Tab to view them while inputting.

Click [Compute]. Then click the Charts tab to view the results in graphical form.

Modified Rational method hydrographRemember, the idea behind the Modified Rational method is to find a total duration that maximizes the blue-shaded region you see in the above chart. The Storm Duration Factor (SDF) is what is being calculated by the program. In this chart, the SDF = 7.2. Thus 7.2 x Tc + Tc = 98.4 minutes total duration. In the Standard Rational, SDF = 1.0.

Here are the charts overlaid. Do this by selecting Hydrographs 1 and 2 while holding the [Shift] key down.

Modified Rational Method

Step 3. Design a Detention Pond

Now that we have created the pre-and post-developed hydrographs, we can design a detention pond with release rates that match the Pre-developed Qs. Again, the pre-developed peak Qs are 7, 10 and 15 cfs for the 2, 10 and 100-year events respectively.

Hydrology Studio uses a three-step procedure for easy detention pond design.

Step 1. Estimate Required Storage

We clicked on the [Pond] button on the top toolbar which opened the Pond Designer Window. Here we entered the following:

All we did was select Hydrograph 2 for the “Post-dev Hyd” and Hydrograph 1 for the “Pre-dev Hyd” as shown above in the drop-down list boxes (The Q target inputs will be filled in automatically). Then clicked [Estimate Storage]. The software provided us with an estimate on how large our pond should be… 69,877 cuft. We used this number to build our pond.

Step 2. Create a Detention Pond

We clicked [Create Pond >] to advance to the second step in our detention pond design. As indicated in the previous article, we settled on using a standard Trapezoidal-shaped pond. It must be 8-feet deep; have 1 foot of freeboard; and have 2:1 side slopes. All we needed to do was find a bottom dimension ( L x W) that provided us with a total volume of at least 69,877 cuft at 7 foot of depth. After a few trials of Bottom Length & Width, we arrived at the following 80 x 80 pond.

Keep in mind that the storage estimate in the previous step is just that, an estimate. The final result may be somewhat different. Next we clicked [Outlet Struct >] to advance to the final step.

Step 3. Add Outlet Structures

We wanted to build a multi-stage outlet structure that resembled this:

The Culvert needed to be 50 feet in length at a 0.50% slope. Our aim was to use a 4′ x 4′ box Riser that held a combination of orifices and/or weirs to satisfy our target Q requirements. We did not want the Riser’s top to be used as weir.

We used Hydrology Studio’s interactive features so we first chose to view the Structure Schematic. The screen initially looked like this:

We also made sure to select the 100-yr row on the Trial Route table.

The goal now is to add outlet devices, one-by-one, until we have satisfied our release rate requirements.

Added the Culvert

Designing not by return period but from downstream to upstream, we first added a Culvert using the initial design constraints stated above. Just to get something on the screen, we selected a 12 inch circular culvert. Then clicked [Add/Update], and then [Trial Route].

As shown on the Trial Route table above, the 100-year event failed. If you click on the Trial Route radio button you’ll see exactly when and where it failed. Obviously we needed to increase the size of the Culvert so we increased the 12 to a 15-inch. Then clicked [Add/Update] and [Trial Route] again. The routing succeeded but the Q actual fell just short of our Target and it left a little more freeboard than we wanted. We want to make the most of our pond storage.

We settled for an 18-inch. Yes, its Q Actual will exceed the target but that’s the point. We want the Culvert to be large enough to pass the 100-yr return period, not less. We’ll use secondary structures to control the 100-yr event. (This is a typical scenario due to being limited to commercially available pipe sizes). If you can’t closely reach your target Q (rarely happens), go to the next size up.

Added the Riser

We knew we would be using a Riser as a container for the secondary devices, so we added it next. This also helps the visual. We added the data but did not attempt a Trial Route because nothing can escape the pond now. The inputs are as follows:

We set the crest elevation high so it won’t contribute to outflow. Can be adjusted later.

With only a Culvert and Riser, the pond schematic looked like this:

Added the Orifice (2-Yr)

The next structure to be added (working downstream to upstream) is the orifice, which corresponds to the 2-year event. We used Orifice 1. Like the Culvert, we made a first guess at the size. A 12-inch orifice data is as follows.

Then clicked [Add/Update] and [Trial Route]. The routing succeeded but the 2-year Q Actual fell short of our Target of 7 cfs. We simply made size adjustments upwards while performing Trial Routes until we met our 2-year target. That size was 14 inches. The structure (front view) now looked like this as it displays the routed 2-yr water surface.

We noted the maximum 2-year water surface elevation of 103.69. This will be the elevation at which we set our next upstream structure, corresponding to the 10-year event. You’ll see this on the Trial Route table below.

At this point do not pay attention to the 10 and 100-year events. Those come next.

Added the Orifice (10-Yr)

Note that we first attempted to use a rectangular weir as shown in multi-stage structure above but we could not satisfy both 10 and 100-year events without overflowing the Riser. This is typical of a Modified Rational inflow hydrograph due to its linear shape along its peak line.

The next structure to be added (working downstream to upstream) is another orifice (Orifice 2), which corresponds to the 10-year event. Like Orifice 1, we made a first best guess at its size of 12-inches. We set its invert elevation to just-above the maximum elevation of the 2-year routing at 103.70. Then clicked [Add/Update] and [Trial Route].

The first routing exceeded the target Q but after making adjustments and performing Trial Routes, we quickly arrived at 8.25 inches. Here is the resulting structure and trial routing results.

Added the Orifice (100-yr)

The 2 and 10-year events are complete and close to perfect. Moving further upstream we added a final orifice, Orifice 3, to satisfy the 100-year.

Remember, the Culvert was sized too large to be used for this event so we knew we would need to add a separate secondary structure for this as well.

We simply repeated what we had done for the previous orifice. We added our standard best-guess 12-inch and set its invert at the maximum water surface elevation reached during the 10-year event routing at 105.00. Inputs are:

Then clicked [Add/Update] and [Trial Route]. The routing succeeded but the Q Actual exceeded our Target of 15 cfs. We simply made size adjustments downwards while performing Trial Routes until we met our 100-year target. That size was 9.25 inches.

Here is the final structure and the routing results.

This was our final design

Near perfect routing results. Note that we honored our 1-foot of freeboard within 0.01 feet.

Step 4. Perform the final Pond Routing

Once our pond design was completed, we clicked the [Finish] button to close out the Pond Designer and return to the Basin Model. Even though the pond structure was designed, we still needed to finish out the basin model and perform the real routing.

We selected Hydrograph 2 (Post Mod) and clicked the [Route] button on the Ribbon toolbar. This added the Pond Route icon to the Basin Model.

Modified Rational MethodSelecting the newly added icon populates the Pond Route input window as shown below.

We gave it a name, “Mod Rational Pond”, and clicked [Compute].

Here is the final result.
Modified Rational Method examples

The Modified Rational method assumed a required storage of 69,789 cuft. The actual was about 10 percent less at 62,229 cuft. This is due to the concave shape of the outflow hydrograph rather than a straight line.

Conclusion

Hopefully this article provided some insights into the Modified Rational method and the proper steps to take when designing a detention pond.

Always use the Standard Rational for the pre-developed condition. Take those peak Qs and enter them as Target Qs in the post-developed condition using the Modified Rational method. The Modified Rational method hydrograph will be used as the Inflow into your detention pond routing.

Always build your pond outlet structures by adding them in the order from downstream to upstream. Size them to satisfy their corresponding return period release rates before moving to the next upstream structure. Set their inverts equal to the Max. Elevation reached during the previous structure’s routing. Avoid using the Riser as a controlling device.

 

Was this article helpful?

Related Articles